Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 11, 2020 Pdfprep2020-11-11T16:26:18+00:00 The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?A . 10B . 12C . 14D . 16 View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.