Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 3, 2020 Pdfprep2020-11-03T01:43:38+00:00 Lessons learned are created and project resources are released in which Process Group?A . PlanningB . ExecutingC . ClosingD . Initiating View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.