The primary benefit of the Plan Schedule Management process is that it:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The primary benefit of the Plan Schedule Management process is that it:
A .  provides guidance to identify time or schedule challenges within the project.
B .  tightly links processes to create a seamless project schedule.
C .  guides how the project schedule will be managed throughout the project.
D .  creates an overview of all activities broken down into manageable subsections.

Answer: C