Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 13, 2020 Pdfprep2020-10-13T17:28:01+00:00 The Perform Integrated Change Control process occurs in which Process Group?A . InitiatingB . ExecutingC . Monitoring and ControllingD . Planning View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.