Based on the chart, what is the schedule variance (SV) for Task 8?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule variance (SV) for Task 8?
A .  -2,000
B .  -1,000
C .  1,000
D .  2,000

Answer: B