The Plan Stakeholder Management process belongs to which Process Group?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The Plan Stakeholder Management process belongs to which Process Group?
A .  Executing
B .  Initiating
C .  Planning
D .  Monitoring and Controlling

Answer: C