Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 4, 2020 Pdfprep2020-11-04T13:26:44+00:00 The Plan Stakeholder Management process belongs to which Process Group?A . ExecutingB . InitiatingC . PlanningD . Monitoring and Controlling View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.