The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
A .  Planning.
B .  Executing,
C .  Monitoring and Controlling.
D .  Closing.

Answer: C