The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
A .  Earned value management.
B .  Forecasting.
C .  Critical chain methodology.
D .  Critical path methodology.

Answer: A