Which of the following tools or techniques is used for Estimate Activity Durations?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which of the following tools or techniques is used for Estimate Activity Durations?
A .  Critical path method
B .  Rolling wave planning
C .  Precedence diagramming method
D .  Parametric estimating

Answer: D