Which project document is updated in the Control Stakeholder Engagement process?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which project document is updated in the Control Stakeholder Engagement process?
A .  Project reports
B .  Issue log
C .  Lessons learned documentation
D .  Work performance information

Answer: B