Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 13, 2020 Pdfprep2020-10-13T10:00:02+00:00 An input of the Plan Procurement Management process is:A . Make-or-buy decisions.B . Activity cost estimates.C . Seller proposals.D . Procurement documents. View Answer Answer: B Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.