Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
A .  Project Integration Management
B .  Project Communications Management
C .  Project Information Management System (PIMS)
D .  Project Scope Management

Answer: B