Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: December 6, 2020 Pdfprep2020-12-06T06:37:26+00:00 The following is a network diagram for a project. The free float for Activity E is how many days?A . 2B . 3C . 5D . 8 View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.