Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 15, 2020 Pdfprep2020-10-15T03:30:30+00:00 An input to Develop Project Charter is a/an:A . Business case.B . Activity list.C . Project management plan.D . Cost forecast. View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.
Leave a Reply