Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 14, 2020 Pdfprep2020-10-14T20:35:07+00:00 The following chart contains information about the tasks in a project. Based on the chart, what is the cost performance index (CPI) for Task 2?A . 0.8B . 1C . 1.25D . 1.8 View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.