The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
A .  Continuous improvement.
B .  Predictive planning.
C .  Progressive elaboration.
D .  Quality assurance.

Answer: C