Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project’s:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project’s:
A .  Level of control.
B .  Communication channels.
C .  Scope.
D .  Strategic alignment.

Answer: A