Inputs to the Plan Schedule Management process include:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Inputs to the Plan Schedule Management process include:
A .  Organizational process assets and the project charter,
B .  Enterprise environmental factors and schedule tools.
C .  Time tables and Pareto diagrams.
D .  Activity attributes and resource calendars.

Answer: A