The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
A .  Estimate Costs
B .  Control Costs
C .  Plan Cost Management
D .  Determine Budget

Answer: D