An input to the Plan Stakeholder Management process is:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

An input to the Plan Stakeholder Management process is:
A .  The project charter.
B .  The stakeholder analysis.
C .  Acommunication management plan.
D .  Astakeholder register.

Answer: D